Despite being given an initial payment of P111.23 million and an additional P95.77 million, amounting to P207 million in total for the construction of 2,559 units in four municipalities of Eastern Samar alone—only 36 units (or 1.41 percent) were completed when the contract worth P741.53 million was terminated on Nov. 27, 2017. Based on PACC’s continue reading : PACC urges Ombudsman to file charges against 12 NHA Officials over unfinished Yolanda housing projects